WELCOME

630 Ha Site in the North mainland

Average wind speed of 11m/s

Adjacent to Oil & Gas infrastructure
IN SHETLAND
BY SHETLAND
FOR SHETLAND

10
Turbines

200m
Turbine Height

50+MW
Generating Capacity

25MW
Battery Storage

40yrs
Operating Period

ABOUT THE PROJECT

PROJECT TIMELINE
Please note that our project timeline may be subject to change.

Project Conception & Site Selection
2003

Data collection & surveys
2021-2025

Grid Connection Application
2023

Feasibility studies
2024

Scoping submitted to the ECU
Mar 2025

Public Engagement Event
Mar 2025

Environmental Impact Assessment
Mar-Nov 2025

Second Public Engagement Event
Aug 2025

Planning Application & EIAR Submission
Nov 2025

Anticipated Consent
2026-2027

Construction
2028-2030

Operation
2030-2070